%%{init: {"flowchart": {"diagramPadding": -480, "rankSpacing": 25, "nodeSpacing": 30}}}%%
flowchart TD
A(["RFQ / RFP Received"]) --> B["Register Opportunity, Assign Tender Team and Deadline"]
B --> C["Review Scope, Eligibility, Capacity and Commercial Risk"]
C --> D{"Bid / No-Bid?"}
D -- No --> E["Record Decision and Close Opportunity"]
E --> E1(["Tender Closed"])
D -- Yes --> F["Receive IFP & Technical Documents"]
F --> G["Review and Raise Client Clarifications"]
G --> H["Assign Estimators"]
subgraph EST["PARALLEL ESTIMATION AND VENDOR QUOTATIONS"]
direction TB
H --> I["Quantity Take-Offs and Cost Calculations"]
I --> J["Civil Estimate Consolidated by Civil Lead Estimator"]
I --> K["Other Works Estimate Consolidated by Lead Estimator"]
I --> L["Identify Specialist / Design Packages for External Quotes"]
L --> M["Prepare and Issue Vendor / Specialist RFQs"]
M --> N["Receive and Log Quotations"]
N --> O{"Quotes Complete and Compliant?"}
O -- No --> P["Follow Up, Clarify or Request Revised Quotes"]
P --> N
O -- Yes --> Q["Compare Scope, Exclusions, Price, Delivery and Validity"]
Q --> R["Confirm Quoted Costs"]
J --> S["Consolidate All Cost Inputs"]
K --> S
R --> S
S --> T["Complete Cost Build-Up, Risks, Contingency and Margin"]
end
T --> U["Technical Management Review"]
U --> V["Submit Bid to Client"]
V --> X{"Clarification, Revision or Rebid?"}
X -- Yes --> Y["Review Addenda, Clarifications and Revised Scope"]
Y --> Z["Reassess Affected Quantities, Estimates, Vendor Quotes and Pricing"]
Z --> U
X -- No --> AA["Follow Up if Required"]
AA --> AB{"Final Client Outcome?"}
AB -- Rebid / Requote --> Y
AB -- No Award --> AC["Record Outcome, Reasons and Lessons Learned"]
AC --> E1
AB -- Award --> AD["Project Awarded"]
%% POST-AWARD PROJECT START
AD --> AD1["Handover & Project Kickoff"]
AD1 --> AE["Project Baseline: Scope, Budget, Schedule, Resources and Execution Plan"]
AD1 --> AF["Pre-Construction Submittals"]
%% AD1 --> AG["Engineering, Material Approvals, Permits and Site Readiness"]
AD1 --> PR["Procurement Workstream"]
%% ENGINEERED ITEMS PROCUREMENT
%%PR --> ENG["Engineered Items"]
PR -- "Engineered Items" --> ENG1["Prepare and Issue RFQ"]
ENG1 --> ENG2["Technical / Commercial Evaluation"]
ENG2 --> ENG3["Submit Technical Review for Approval"]
ENG3 --> ENG4["NMR-601"]
ENG4 --> ENG5["NMR-602"]
ENG5 --> ENG6["IAP Approval"]
ENG6 --> ENG7["Pre-Inspection Meeting"]
ENG7 --> ENG8["Inspection Inquiry / Before-Delivery Inspection"]
ENG8 --> ENG9["Delivery"]
ENG9 --> ENG10["MRI - Material Receiving Inspection"]
ENG10 --> ENG11["Spare Parts Data Package Approval"]
%%ENG11 --> ENG12["Engineered Materials Released as Applicable"]
%% MAJOR / BULK CONSTRUCTION PROCUREMENT
%%PR --> BULK["Major / Bulk Items"]
PR --"Major / Bulk Items"--> BULK1["Prepare and Issue RFQ"]
BULK1 --> BULK2["Technical / Commercial Evaluation"]
BULK2 --> BULK3["Purchase Order"]
BULK3 --> BULK4["Delivery"]
BULK4 --> BULK5["MRI- Material Receiving Inspection"]
%% CONSTRUCTION READINESS
AE --> READY["Construction Readiness"]
AF --> READY
%% AG --> READY
ENG11 --> READY
BULK5 --> READY
%% CONSTRUCTION AND QUALITY CONTROL
READY --> AH["Construction and Installation"]
AH --> AI["Contractor QC Checks and Submit Inspection Request"]
AI --> AJ["Client / Aramco Inspection"]
AJ --> AK{"Inspection Accepted?"}
AK -- No --> AL["Rectify Defects / NCR and Take Corrective Action"]
AL --> AI
AK -- Yes --> AM["Record Acceptance and Continue Work"]
AM --> AN{"All Construction Complete?"}
AN -- No --> AH
AN -- Yes --> AO["Mechanical Completion and Punch List"]
%% COMMISSIONING AND CLOSEOUT
AO --> AP["Pre-Commissioning and Commissioning"]
AP --> AQ{"Tests Accepted?"}
AQ -- No --> AR["Correct Defects, Retest and Reinspect"]
AR --> AP
AQ -- Yes --> AS["As-Builts, Quality Dossier and Client Handover"]
AS --> AT["Final Quantities, Variations, Claims and Final Account"]
AT --> AU["Invoices, Retention and Supplier / Subcontractor Settlement"]
AU --> AV["Warranty / Defects Period and Outstanding Rectifications"]
AV --> AW(["Archive Records & Close Project"])
%% CONTINUOUS CONTROLS
%% CTRL[["CONTINUOUS CONTROLS
Document Control - HSE - QA/QC
Schedule - Cost - Change Control"]]
%%CTRL -.-> AH
%%CTRL -.-> AP
%% STYLING
classDef primary fill:#0A3B2B,color:#FFFFFF,stroke:#0A3B2B,stroke-width:2px
classDef awarded fill:#0A3B2B,color:#FFFFFF,stroke:#C4BC96,stroke-width:5px
classDef process fill:#C4BC96,color:#172E26,stroke:#0A3B2B,stroke-width:1px
classDef decision fill:#FFF0CC,color:#543B0B,stroke:#B79A55,stroke-width:1.5px
classDef rework fill:#FCE5E1,color:#8B2418,stroke:#C74732,stroke-width:1px
classDef controls fill:#E8EFEA,color:#0A3B2B,stroke:#0A3B2B,stroke-width:1.5px
classDef planning fill:#E8EFEA,color:#0A3B2B,stroke:#0A3B2B,stroke-width:1.5px
classDef procurement fill:#C4BC96,color:#172E26,stroke:#0A3B2B,stroke-width:1.2px
class A,E1,AW primary
class AD awarded
class B,C,F,G,H,I,J,K,L,M,N,Q,R,S,T,U,V,W,AA,AC,AD1,AH,AI,AJ,AM,AO,AP,AS,AT,AU,AV process
class D,O,X,AB,AK,AN,AQ,PR decision
class P,Y,Z,AL,AR rework
class CTRL controls
class AE,AF,AG,READY planning
class ENG,ENG1,ENG2,ENG3,ENG4,ENG5,ENG6,ENG7,ENG8,ENG9,ENG10,ENG11,ENG12,BULK,BULK1,BULK2,BULK3,BULK4,BULK5 procurement